First L-N-G Tanker Due Monday

The first tanker carrying liquefied natural gas for the new Canaport L-N-G terminal is due Monday. The first tank is ready to receive liquefied natural gas, and will under go a cooling process once the shipment arrives. The flare will be visible near the seaside of the terminal located off Red Head Road in Saint John’s East end for up tp 10 days. Energy Minister Jack Keir says this marks the start of Saint John being the energy hub.The second natural gas tank will be operational next month with the third and final tank accepting product by the end of the year. MeanwhleAs part of the normal commissioning process, Canaport LNG will engage its safety release flare system which will be visible from some vantage points within Saint John for up to 10 days.